zref:ats:inteli [2024/09/21 22:35] Alan Sheazref:ats:inteli [2025/10/30 21:02] (current) – [Utility Power Return] Alan Shea
Line 51: Line 51:
   - If utility power fails to return within 5 seconds:    - If utility power fails to return within 5 seconds: 
     - InteliATS closes KGS [6] to start the genset     - InteliATS closes KGS [6] to start the genset
-  - Once the generator is running, the Inteli:zref:ats: +  - Once the generator is running, the InteliATS 
     - Qualifies input for minimum, maximum voltage on all phases, correct phase rotation, minimum, maximum frequency     - Qualifies input for minimum, maximum voltage on all phases, correct phase rotation, minimum, maximum frequency
     - Illuminates L-G (Blue) indicating generator power is OK.     - Illuminates L-G (Blue) indicating generator power is OK.
Line 61: Line 61:
  
 ====Utility Power Return== ====Utility Power Return==
-  - When Utility Power returns, Inteli:zref:ats: +  - When Utility Power returns, InteliATS 
     - Qualifies input for minimum, maximum voltage on all phases, correct phase rotation, minimum, maximum frequency     - Qualifies input for minimum, maximum voltage on all phases, correct phase rotation, minimum, maximum frequency
     - Indicator L-U (Green) illuminates to confirm utility grid voltage is acceptable     - Indicator L-U (Green) illuminates to confirm utility grid voltage is acceptable